Yardleys School, Birmingham
The construction of a new extension – all carried out within a live working educational environment.
£0.9m
Project Value
Project Duration
Project Yardleys School
Location Birmingham
Client Yardleys School / Galliford Try FM
Project Description The construction of a new school extension block comprising a steel frame, SFS infill, precast concrete ground floor, single ply roofing on a steel deck, Rainscreen cladding, aluminium windows & doors, extensive Mechanical and Electrical Installations, FF&E fitting out.
Project Value £ 0.9M
Project Duration 26 Weeks
Form of Contract JCT Standard form of Building Contract with Quantities
Design Team Tweedale Ltd Architects, ASC Design Ltd, CJR Midlands Ltd, Faithful+Gould Ltd, Galliford Try Facilities Management.
Procurement Competitive single stage tender
A big thank you to AMG and especially Steve Gandy [AMG site manager] who worked so well with the design team and the school throughout the project, keeping the school informed and involved from beginning to end and succeeding in delivering the project with minimal disruption to the smooth running of the school.