King Charles Primary School, Walsall
“A very good relationship was built and developed during the contract period between AMG and the Client’s professional team
AMG’s enthusiasm and ‘can do’ attitude enabled a high quality job to be delivered in a live educational environment, with minimal disruption to the school”
A new single storey classroom unit in our RoWeR System, and extensive refurbishment of the existing school, carried out within a live working educational environment.

£0.65m
Project Value
Project Duration
Location Wilkes Avenue, Walsall WS2 0JN
Client Walsall Council
Project Description AMG have successfully completed the Design & Build of a new single storey classroom unit. Following extensive enabling works and relocation of school buildings, features and equipment, the new building benefited from the speed and flexibility of our RoWeR system, constructed with engineered foundations, taking into account the local mine workings, and a bespoke steel frame. The external walls comprise Trespa rainscreen cladding panels. The roof is made up of cold rolled steel & composite cladding insulation panels with a single ply membrane. Internal walls are lightweight partition construction. Extensive new M&E installations, incoming services, drainage and external works comprising new play areas, parking and covered educational spaces.
Project Value £0.65M
Project Duration 20 Weeks
Form of Contract JCT Design & Build
Design Team G.H. Design Ltd, Central Design Consultants Ltd
Procurement Competitive single stage selective tender – Design & Build
Case Study – King Charles Primary School, Walsall
“A very good relationship was built and developed during the contract period between AMG and the Client’s professional team
AMG’s enthusiasm and ‘can do’ attitude enabled a high quality job to be delivered in a live educational environment, with minimal disruption to the school”