Hybrid Theatre, Heartlands Hospital

Project Description

The construction and commissioning of a new build Hybrid Theatre at first floor level at Birmingham Heartlands Hospital, undertaken within tight deadlines as required by The Heart of England NHS Foundation Trust.

£2.4m

Project Value

Project Duration

Location Bordesley Green , Birmingham

Client The Heart of England NHS Foundation Trust

Project The construction and commissioning of a new build Hybrid Theatre at first floor level at Birmingham Heartlands Hospital within and alongside “live and occupied” buildings and departments in the heart of the hospital complex. The construction of the new theatre building, installation of extensive services and specialist equipment, including Specialist laser and robotic theatre equipment, together with the construction of a new plant room immediately below to support the new Hybrid Theatre development was undertaken within tight deadlines as required by The Heart of England NHS Foundation Trust.
The work also necessitated modifications and refurbishment to the areas immediately adjacent to the new theatre and the supporting services installations, including ventilation, air conditioning, IPS and UPS equipment.

Project Value £ £2.4M

Project Duration 38 Weeks

Form of Contract JCT contract with Quantities

Design Team Horsley Huber Architects, Couch Consulting Engineers, Stewart Associates, 

Procurement Competitive single stage tender