Coventry University Hub Cafe
The construction of the new hub facility, carried out within a live working educational environment.
£2.65m
Project Value
Project Duration
Project Coventry University Hub Cafe enclosure
Location
The HUB Building
Coventry University
Jorden Well
Coventry
CV1 5RW
Client Coventry University
Project Description The works were carried out in the heart of the existing campus comprising the strip out and demolition of existing areas together with the enclosure of an existing open courtyard with a new steel frame roof and glazed external façade. The works included demolition of internal walls, a new structural slab within the existing courtyard, M&E fit out including underfloor heating, new wall and floor finishes, new furniture, servery and catering equipment and the refurbishment of ground floor ancillary areas, all carried out within a live working educational environment.
Project Value £2.65M
Project Duration 40 Weeks
Form of Contract JCT IFC with Contractors Design
Design Team Broadway Malyan, Osbournes Quantity Surveyors, Pick Everard, Hydrock
Procurement Competitive single stage tender